Initiatives

CAPITAL PROJECTS

ENGINEERING

A. Village Capital Projects

1. Pierson Road Bridle Trail – 800’ east of South Shore to Southfields Road
Status Update: The Engineering Department is completing the design and construction documents. Construction is anticipated in July 2017.

2. South Shore Boulevard/Pierson Road Intersection Improvements
Status Update: The Work Order with Mock Roos for the intersection PD&E study and cost estimate development was approved at the April 12th Council meeting. The design/permitting kickoff meeting took place on April 18th. The project is currently under design.

3. Scott’s Place – Lighting and Shade Improvements
Status Update: Smith Engineering has been authorized to complete the lighting and camera design. The shade structure construction documents are currently being designed in-house. Construction of shade structures is a priority and is anticipated to commence this summer.

4. Pierson Road / South Shore Blvd. Northbound Right Turn Lane Extension
Status Update: 100% design plans are complete. The bids were received on April 19th. Construction is anticipated to commence in May/June 2017.

5. Big Blue Trace/Barberry
Status Update: Survey and design work is currently underway. Construction is anticipated to commence in July 2017.

6. Big Blue Trace/Wiltshire
Status Update: Survey and design work is currently underway. Construction is anticipated to commence in July 2017.

7. Forest Hill Boulevard/C-8 Canal Improvements
Status Update: Survey and design work are currently underway. Construction is anticipated to commence in March 2018.

8. Forest Hill Boulevard C-13 Canal Culvert Replacement Project:
Status Update: Construction is substantially complete.

9. Public Works Retention Area Project
Status Update: The project is on-hold until the site master plan is complete.

10. Stribling Road/Fairlane Farms Road Round-a-Bout Landscape
Status Update: The irrigation pump has been delivered and is currently being installed. The landscaping installation will commence shortly after the installation of the irrigation system.

11. Wellington Community Center
Status Update: The contractor continues to finalize the punch list items for the project. Weekly punch list walkthrough’s are being performed until Final Completion. Currently, the Engineering Staff has been negotiating close out issues (change orders and punch list items) with the contractor. Final project closeout is anticipated in 60 days.

12. Hawthorne Neighborhood Park Project:
Status Update: Construction is anticipated to be completed in August 2017.

13. Dorchester Park Observation Platform
Status Update: The project is currently in the design and permitting phase. Construction is anticipated to commence in July 2017.

B. Village of Wellington Assessment Projects

1. Saddle Trail Park (South) Neighborhood Improvement Project
Status Update: The contractor portion of the project is complete. The material for the horse crossing signage and lighting has been received and is currently being installed.

C. Miscellaneous Projects

1. Forest Hill Boulevard Sink Hole Repair Status Update: The project is scheduled to be under construction on June 5th. This will be after school lets out for the summer break.

D. Permitted Projects

1. 40th Street Improvements – C-4/C-24 Culvert Project:
Status Update: The culvert project is complete. The developer constructed 40th Street roadway project is listed to be completed by May 1st. Staff’s review indicates another 90 + days to completion.

UTILITIES – Capital Projects

Water Supply Improvements

Raw Water Supply Evaluations: Kimley Horn Authorized January 25th

- Completion Date March 2017
- Preliminary Data Received March 28th
- Final Report Recommendations within 2 weeks

Consumptive Use Permit Analysis: JLA Geosciences authorized December 17, 2016

- Initial review completed; two meetings conducted with SFWMD
- Preliminary report reviewed and approved by Staff
- Final report to be received within 1 week

Comprehensive Water Supply Plan Initial Meeting with SFWMD occurred in Februrary
- Included in 2018 Capital
- Goal to have Work Authorization to Council in October 2017

Water Recharge Evaluation: Higgins Engineering Authorization Pending
- Diversion and Impoundment Permit Review

Water Supply Well Rehabilitation: Contract with All Webbs Enterprises Approved
Work on hold pending recommendations from Raw Water Supply Evaluations

Water Treatment Plant Improvements

WTP Residuals Handling Analysis Kimley Horn PO issued February 22nd.
- Evaluation has commenced
- Preliminary report scheduled for May 2017

2017 Renewal and Replacement Kimley Horn Authorized January 25th
- Design Completion Date May 2017 – On Schedule
- Design finalization ongoing. Project on schedule.

Fluoride System Installation Kimley Horn authorized July 2016

Design completion May 2017
PBCHD Permit Issued February 8, 2017
- Design finalization ongoing
- Completion scheduled for January 2018,, to be included with the WTP R and R 2017 project
- Interim installation online May 16, 2017

Lime Plant Replacement Kimley Horn scope and fee approved by staff
- Scope includes master plan evaluation to replace the Lime Plant which is over 35 years old with membrane treatment
Work Authorization to Council on May 23, 2017

Water Reclamation Facility Improvements

2017 Renewal and Replacement Kimley Horn: Authorization to Council February 28th
- Design completion date July 2017
- Design finalization ongoning
- Project on schedule